M1-M2 Tunnels – Southern Interchange Underbores

Project Overview

Pennant Hills Road connects the M1 and M2 motorways through North Sydney and has long been one of Sydney’s most unpopular roads due to its high traffic volumes and delays. The M2 Southern Interchange tunnel project was constructed to solve this by connecting the two motorways with two direct, three-lane tunnels – one for each direction of traffic flow. These tunnels will reduce travel time by fifteen minutes and take over 5,000 heavy vehicles per day off Pennant Hills Road. UEA was engaged to completed multiple underbores for the project in order to accommodate electrical and telecommunications services.

Location

Carlingford NSW

Geology

Sandstone & siltstone

Client

LendLease Bouygues Joint Venture

Length

2x 230 metres of HDD

Pipe

7 x 75mm PN16 PE100 HDPE, 5 x 125mm PN16 PE100 HDPE, 3 x 200mm PN16 PE100 HDPE

Technique

HDD & free bore

Scope of Works

UEA completed the construction of two 230 metres underbores as a part of the construction of the tunnels connecting the M1 & M2 motorways. Both bores were 550mm in diameter and were constructed from a new switching station site across the existing M2 motorway. As the project was extremely technical in nature, UEA was involved in the design of the two underbores as part of the Early Contractor Involvement stage of the project. With a separation of 2.4 metres from centre to centre, the underbores were designed to avoid obstructions such as the existing piles and rock anchors for the newly constructed tunnels. This increased the difficulty of the job as it led to alignment constraints of both underbores. As a result, UEA utilised wireline technology to track the underbores to ensure that these obstructions were avoided while crossing the M2 motorway through what was the only remaining window between these two points. Electrical cables were installed into Bore 1 whilst Bore 2 consisted of LV & communications cables.

Challenges

Due to the limited footprint allowed onsite for the underboring works, UEA had to maximise the efficiency of the selected plant in relation to the provided footprint. Plant and equipment that was utilised within the entry side at the switching site included the Vermeer D100 HDD rig, 13T & 22T excavators, cleaning systems and mud pumps. UEA also increased efficiency by using drilling fluid recycling and storage systems at both the entry and exit sides of the bore. This minimised the overall project impacts and reduced both vehicle movements and the project’s timeframes. As there was very minimal area for UEA to operate at the exit side – which was situated in the M2 shaft – UEA limited the underboring activities at the exit side to include:

  • the confirmation of pilot bore punch out
  • change out of drilling tooling
  • primary processing of drilling fluid returns and pumping back to entry side.

Additionally, as our crews were working within the confines of the tunnel construction crews, the focus on managing the interfaces between a number of work groups was challenging. As there was a requirement to maintain the frequency of vehicles accessing the tunnel throughout the project, a forward reaming methodology was undertaken from entry side. This enabled the drill mud to be managed from the surface allowing ease of access to the recycling system and vacuum trucks. Once reaming activities were completed, the HDD rig was relocated to exit into the adit that was only slightly wider that the length of the HDD rig itself.

There were several constraints and difficulties throughout the duration of this project, however successful completion was achieved through careful planning and ongoing design development. Based on the successful completion of the HDD portion of the project, UEA was awarded further bores to continue works on this project, consisting of a thrust bore 36 metres in length to cross between an adit and principal tunnel, and a further seven ‘free’ bores drilled between tunnels sitting 10-15 metres above each other, with a combination of guided boring and horizontal drilling technologies.

UEA utilised a number of underboring techniques in order to achieve required outcomes in challenging situations, including but not limited to:

  • Drilling at significantly steep grades, withbores ranging from angles of 20-64%. With consideration to site requirements and general safe work practices, UEA utilised a range of plant and machine to safely drill and install conduits.
  • Assisted in design and excavation of launch and receival pits to meet design, spatial and safety restrictions.
  • Regular co-ordination of deliveries, cranes, traffic control and surveyors in conjunction with both the client as well as other subcontractors.
  • Accelerated completion date as requested by client. UEA utilised a range of options to deliver the project in a quicker timeline with minimal financial impact to the client.

Completion

UEA’s HDD crews worked tirelessly to meet and exceed all of the project deadlines and challenges, and to comply with all HSEQ requirements. UEA was able to complete this challenging project requiring our team’s knowledge and expertise in order to utilise a range of innovative techniques to safely deliver the works.

Share on facebook
Share on google
Share on twitter
Share on linkedin

LEARN MORE ABOUT OUR PROJECTS OR TELL US ABOUT YOURS