AGNES WATERS / 1770 OCEAN OUTFALL

Project Overview

UEA was contracted by TRILITY to install a 600 metre section of 630mm PE pipe via horizontal directional drilling (HDD) for the raw sea water intake of the new desalination plant being constructed for Agnes Waters/Seventeen Seventy.

Location

Agnes Waters / 1770 QLD

Geology

Rock

Client

TRILITY

Length

610 metres

Pipe

630mm PN 16 PE100 polyethylene

Technique

HDD ocean outfall

Scope of Works

The installation of the last ocean outfall pipeline for the raw seawater intake needed to be completed before turtle season – within a short timeframe, UEA mobilised a HDD maxi rig spread to undertake the remaining scope. UEA and TRILITY agreed to use the abandoned bore which had to be re-surveyed during the pilot hole installation. The bore was deemed usable as long as the exit could be plugged and
professionally grouted for a safe exit angle through the rock formation. A 150-metre section at the exit point, 550 metres out, was grouted and once set UEA re-piloted the borehole and exited into the ocean floor at CH 610. Two reaming passes were completed out to 32 inches before a cleaning pass with the pipe installed over a 12-hour period.

CHALLENGES

Many challenges had to be managed for this project to be successful, including: short timeframe, isolated location, tooling requirements from overseas, co-ordination of numerous highly skilled contractors, complicated diving works for underwater tooling connections, and environmental impacts.

COMPLETION

UEA’s experience ensured that challenges were managed efficiently, and the project was successfully delivered one day before the first turtle wandered up onto the beach.

Share on facebook
Share on google
Share on twitter
Share on linkedin

LEARN MORE ABOUT OUR PROJECTS OR TELL US ABOUT YOURS