Shannon Creek Storage Facility Project

Leighton-LogoThe Shannon Creek Storage Facility project undertaken by Leighton Contractors on behalf of the Clarence Valley Council and North Coast Water provides 30,000 megaliters of water storage for the towns of Coffs Harbour and Grafton in northern New South Wales. The population of this region is projected to grow from 90,000 to 220,000 by the year 2050. An environmentally protected escarpment forms one wall of the dam which presented an engineering challenge as a natural barrier to bringing communications and power services into the dam as well as taking water away from the dam. As the escarpment is 50 – 60 metres in height above the level of the pumping station, it also adds difficulty to the task of pumping water from the dam.

The scope of work encompassed four straight bores, each approximately 330 metres, to link with services laid up to the eastern side of the escarpment. The bores were to house a 110 mm diameter communications conduit, two 140 mm diameter electrical conduits and a 900 mm water main. Because of environmental constraints a geotechnical investigation could only be conducted in the valley areas. The sandstone outcrop surrounding the Shannon Creek area was estimated at 40 – 60 Mpa (5800 –8700 psi). The project was ideal for the Vermeer D300x500 HDD rig, as its rail could be positioned horizontally against the vertical face of the escarpment, facilitating the six percent upward grade required for the bore. A Digitrak Eclipse Steering Tool was used to guide the pilot bores through the escarpment to the exit point. While drilling the pilot bores UEA encountered harder than expected ground conditions. Based on the findings the intended style of reamer for the large diameter cut would be inadequate. A 42” (1066mm) hole opener was used to cut through the 120 Mpa (17,400 psi) rock. The grade of the bore hole ensured that it was self cleaning which eliminated the need for complex drilling muds. Although the water pipe had a 90 tonne dead weight pull back force did not exceed 10 tonnes during the installation.

For more information about this project or UEA Trenchless, please send enquiries to Steven Hopkins.