HDD Underbore on the Ribbon Gas Main Extension Project



Click to Zoom

Project Overview

The Ribbon is the redevelopment of the IMAX Sydney site as part of the ongoing renewal of the Darling Harbour Precinct. It will provide new commercial offices, entertainment and retail/ restaurant facilities within an identifiable landmark building, as well as new public amenities, offices and a workshop for the Sydney Harbour Foreshore Authority (SHFA).

Scope of Works

As part of the Ribbon Development in Darling Harbour, UEA was engaged to undertake extensive utility location with the objective to relocate the existing gas main in Darling Harbour. Stage 1 involved the use of dial before you dig requests, ground penetrating radar (GPR) searches and non-destructive digging (potholing) to identify the location and depth of existing services along the proposed underbore route. Once completed, UEA utilised GIS data to complete an underbore design which mapped all existing services, the new proposed gas route and possible obstructions including the concrete footings for the Western Distributor.

Based on UEA’s experience with completing complex underbores in highly congested locations and the completion of stage 1 works, UEA was also awarded stage 2 of the project following a competitive tender. Working within a brownfields site with over 200 years of redevelopment, historical mapping was utilised to show that the alignment of the underbore would traverse real estate that had changed significantly over the past 75 years.

Without any supplied geotechnical borehole data, the strata to be drilled could not be confirmed before the completion of the pilot bore with the only known ground conditions to be sandstone at the HDD exit point.

Technical Details

Working at night, UEA mobilised and completed a 240 metre underbore using a Ditch Witch AT4020 to install a 110mm PE100 SDR11 gas pipe. The Ditch Witch AT4020 was utilised based on the anticipated mixed ground formation and the known sandstone evident at the HDD exit side. The bore path encountered a number of different ground types including building rubble, clay and sand fill, marine muds and weathered/fresh sandstone. Due to site limitations, pipe was strung out in two 120 metre strings with the final tie in weld being completed during the pull back of the pipe.

For more details on this project or on UEA’s horizontal directional drilling projects, contact the Trenchless team at trenchless@uea.com.au or call us on 02 9672 4456.