Planning & Production

Planning Software

Performance is monitored through the GPS software and daily shift logs. This data is combined with maintenance planning and applied to Microsoft Project.

Flitch cutting durations and sequences are then projected to predict productivity and support requirements for the short to intermediate term future.

Production Rate Measurement

Production rates are measured per pit by using time filters on SVO and combining this report from shift logs to give production rates per pit against multiple variables.

Production rates per pit are applied to the total tonnage of each pit respectively to generate pit turnover rates and forward planning. Microsoft project is used for this application.